Project ID: 1095 | Branch group: Manufacturing Industry | Branch: mechanical and plant engineering
SAP support after the hardware conversion
Project start/end: 01.09.2001 - 31.10.2001
Short description:
After converting the hardware for the entire SAP system, all the system functions are tested and the interfaces, in particular, are altered. The focus here is on the IDOC interfaces with external systems.
Supplement:
First, a trial run is carried out to identify any faults and special features. After the go-live, comprehensive test runs are carried out to test or ensure the system's functions.