Project duration: 10 months

Brief description

Specification, implementation and testing the interface for transferring physical gas flows from the DAISY dispatch system to the Endur trading system for an energy trading company.

Supplement

The project contains the specification, coordation of implementation works by external consultants and test amd introduction of the new interface.

Subject description

The customer plans to use this interface for the transfer of physical gas flows as volume data from the dispatching sytstem to the trading system.

Overview

Project period15.12.2010 - 30.09.2011