Upgrading SAP R/3 4.6C to ERP 6.0

Project duration: 4 months

Brief description

Coordinating and supporting an upgrade project for upgrading SAP R/3 4.6C to SAP ERP 6.0. Enhancement Package 6.0 transferred. The focus is on coordinating the tests and coordinating and performing development work.

Supplement

For the upgrade project, the previous 2-stage system environment is expanded to 3 systems so that the structure of the live system can be tested and a delimited test environment can be provided for the users. After the converted development system has been provided, the work beings with SPDD and SPAU comparisons and the first check of the programs.

Subject description

The tasks of PTA are mainly to plan and complete the project and to perform development work for the custom programs implemented with ABAP. In addition to the invoicing functions, the focus is on modules for project controlling in plant engineering and settlement functions for system engineering orders and service orders that expand the SD functionality.

Overview

Project periodProjektzeitraum01.01.2012 - 30.04.2012

Have we sparked your interest?

Ole Knudsen

Key Account Manager

Jetzt Kontakt aufnehmen

Zum Umgang mit den hier erhobenen Daten informieren wir in unserer Datenschutzerklärung.

Contact now

We provide information on the handling of the data collected here in our privacy policy.

Download file

We provide information on the handling of the data collected here in our privacy policy.